3 Tanks – 1,500,000 Barrels -16 Months Foundation to Coating

2-ariel-view-constructing-three-211'x80'-high-api-650-column-supported-cone-roof-tanks-by-tiw-steel-platework _2_11

** 3 Tanks — 1,500,000 Barrels — 16 Months Foundation to Coating **

TIW completed (3) massive 211’ x 80’ tanks in 16 months for our client in Western Canada. The scope of the project included tank foundations, design, supply and field erection along with hydrotesting, internal lining and external coating.  From start to finish, our team of engineers, project managers and admin staff along with our experienced field supervisors, welders and riggers worked together to achieve the successful execution of another significant tank project. Give us a call today and let’s talk about your next venture!

11-view-from-roof-three-211'x80'-high-api-650-column-supported-cone-roof-tanks-by-tiw-steel-platework _11_11

See More Tank Pictures

 

Learn More About Building Tanks

 

API 650 Tanks, Various Configurations

Related Links

Article written by: Nathan Calford